REAL PROJECT | Riverview, Florida | Drawing coordination documented

Project challenge
A detached ADU needed a coordinated site layout around an existing home, driveway, septic and well infrastructure and mapped wetland constraints.
Source records and documented scope
Project-specific correspondence, drawing descriptions and revision history were reviewed. Confidential source plans and client information are not reproduced.
- Existing house footprint 2,528 SF, concrete and walkways 1,371 SF, driveway 3,435 SF.
- Proposed ADU under-roof footprint 1,452.30 SF; floor area must not be confused with footprint.
- Site plan included property setbacks, utility-route annotations and septic/drainfield coordination.
- Finished-floor elevation shown as 23.60 ft NAVD88; erosion-control/silt-fence information included.
Revisions and coordination
North direction and fill/grading questions were raised in the revision process. A separate engineered grading plan was outside the original site-plan scope.
Current verified status
Site-plan and revised drawing packages documented, including a signed file in the project record. City approval and completed construction are not verified.
Practical permit takeaway
Check survey area totals and existing impervious features before calculating site coverage; verify utility alignments and septic separation in the field.
Project case study PDF
Related permit services
Frequently asked questions
Was the permit approved?
Approval has not been independently verified in the available records.
Are the drawings shown here construction documents?
No. The featured schematic explains documented design considerations; it is not a permit drawing or survey.
Can Site Plans assist with a similar project?
Site-specific drawing scope depends on available survey information, local permit requirements and engineering review needs.