REAL PROJECT | Newport Beach, California | Drawing coordination documented

Project challenge
A non-retaining CMU/stucco perimeter wall required plan and elevation coordination for an approximately 109-linear-foot scope, curved alignment and street visibility.
Source records and documented scope
Project-specific correspondence, drawing descriptions and revision history were reviewed. Confidential source plans and client information are not reproduced.
- Approximately 23 ft of existing wall segment, 35 ft of new 6-ft wall and 51 ft of transitioning wall.
- Continuous height change from 6 ft to 3 ft 6 in along a transitioning segment.
- Curved wall alignment adjusted inward approximately 2 ft in client-requested revisions.
- Column locations, transition limits, drainage/utility access and visibility considerations required coordination.
Revisions and coordination
Client requested transition start/end callouts, added columns at segment boundaries, curve adjustments and end condition at covered entry. Survey-based boundary verification remained important.
Current verified status
Wall plans and revisions documented. No independent confirmation of city approval, final professional sealing or construction completion.
Practical permit takeaway
Treat curved wall geometry, height transitions and corner visibility as a coordinated plan/elevation problem, not isolated notes.
Project case study PDF
Related permit services
Frequently asked questions
Was the permit approved?
Approval has not been independently verified in the available records.
Are the drawings shown here construction documents?
No. The featured schematic explains documented design considerations; it is not a permit drawing or survey.
Can Site Plans assist with a similar project?
Site-specific drawing scope depends on available survey information, local permit requirements and engineering review needs.